Accessibility Tomato World for road works

On 26 November, Trias Westland will start the second phase of the construction of a heat pipe on Zwethlaan. This concerns the construction at the junction with the Broekpolderlaan until just before the junction with the Middel Broekweg (N466). Period 26 November - 21 December 2018 Accessibility of motorised local traffic from Middel Broekweg (N466).

Construction of Zwethlaan heat pipeline at the junction with Broekpolderlaan until just before the junction with Middel Broekweg (N466).
We lay the heat pipe by means of a number of bores and open excavations. 
The work will be carried out by contractor A. Hak, on working days between 6.00 and 20.00 hours. 
Traffic measures for motorised through traffic Zwethlaan 
Planning traffic measures phase 2: 26 November - mid April 2019. Closure of Zwethlaan for through traffic at the junction with Broekpolderlaan until just before the junction with Middel Broekweg (N466).  

For through traffic, detours will be set via Broekpolderlaan, Veilingroute and Middel Broekweg. The diversions are indicated by signs. 
Motorised local traffic traffic measures Zwethlaan 
Residents and companies, located on the Zwethlaan, can use their premises by car/truck. 
during the work. Traffic controllers will supervise local traffic. Residential properties along the route are accessible to the emergency services at all times. 
In the overview below you can see from which road you can reach your house/company:

Period 26 November - 21 December 2018
Accessibility of motorised local traffic from Middel Broekweg (N466).
7 January -22 February 2019
from the junction Zwethlaan-Broekpolderlaan and Middel Broekweg (N466). 
25 February -14 April 2019
From the junction Zwethlaan -Broekpolderlaan