Accessibility Tomato World for road works

Trias Westland will start laying a heat pipeline in Zwethlaan at the beginning of September. 

Zwethlaan and planning activities
We construct the heat conduction by means of a number of drillings and open excavations. The construction will take place in two phases:

Phasing planning
Phase 1: 3 September - 26 November Construction of heat pipeline Zwethlaan
at the roundabout at the Auctioning Route (N222) to just before the junction with Broekpolderlaan. 
Phase 2: 26 November - 1 March 2019 at the intersection with Broekpolderlaan until just before the intersection with Middel Broekweg (N466).
The work is carried out by contractor A. Hak on working days between 6 a.m. and 8 p.m.
Traffic measures through traffic
In order to be able to carry out the work, Zwethlaan will be closed to through motorised traffic in two phases:

Planning traffic measures
Phase 1: 3 September - 26 November Exit from Zwethlaan for through traffic at the roundabout at the Auction route (N222) to just before the crossing with Broekpolderlaan. 
Phase 2: 26 November - 1 March 2019 at the intersection with Broekpolderlaan until just before the intersection with Middel Broekweg (N466). 
For through traffic, diversions (see appendices) are set via Broekpolderlaan, the Auction Route and the Middel Broekweg. The diversions shall be preceded by signs.